Scope of Works
The following were part of the project execution.
Gas Station – Launcher Area: Modification and upgradation for integration with Receiver Station.
Gas Station – Receiver Area: Modification and upgradation for integration with Receiver Station, new control building & PRMS skids, filters and meter skids, Integration of KP3, KP4, Roadbot and Leak detection.
PRMS Station in KP-03 – Design, Supply, Installation, precommissioning and commissioning of New PRS Skids, Flow Meters, Filter and Active Cooling Shelters
PRMS Station in KP-04 – Design, Supply, Installation, precommissioning and commissioning of New PRS Skids, Flow Meters, Filter and Active Cooling Shelters
Gas pipeline works scope shall include Design, supply, Installation, pre-commissioning and commissioning High Pressure & Low-Pressure Pipelines to various KPs.
CRS at Road boat area – Design, Installation, pre-commissioning, and commissioning of CRS at Road bot area.