Scope of Works

Scope of work for Sewerage System

The scope of work for the sewerage network comprises of house connection serving the residential units and the public facilities. The network conveys the sewage flow by a main collector line to a proposed STP. The total length of the Main gravity network is 31 km and house connection is 27 Km.

Sewerage Main Manholes – 442 nos

House Connection Manholes – 1686 nos

Scope of storm water system

The scope of work for storm water in Al Hind 3 comprises a main pipeline length of about 43 km as a gravity system. Based on topography, the Storm water will be discharged to the future DP 08 Pond. The total length of the Main gravity network is 30 km and Gully Network is 12 Km.

Land Drain Netowrk is 12 Km

Storm Water Manholes – 405 nos